Victoria Emergency Backstop — register a Deye system
Check inverter and logger firmware, then register the system for Victoria's Emergency Backstop remote-curtailment requirement via DeyeCloud's Utility Connection Registration.
Updated 29 June 2026
Victoria’s Emergency Backstop mechanism requires new and upgraded solar/battery systems to be remotely controllable, so the network operator can curtail export in rare grid-emergency events. For Deye systems this is done by registering the inverter through DeyeCloud’s Utility Connection Registration.
Confirm before you rely on this. The firmware baselines and registration steps below come from Deye’s own Emergency Backstop instructions. Curtailment rules, eligibility dates and required firmware change over time — always check the current requirements with the customer’s DNSP and Solar Victoria before commissioning.
1. Check the firmware
The inverter and logger must meet the minimum firmware before they can register.
Inverter firmware:
| System | Main | HMI |
|---|---|---|
| Single-phase low voltage | 5388-1516 or higher | 0000-C377 or higher |
| Three-phase low voltage | 1171 or higher | C04F or higher |
| Three-phase high voltage | 1093 or higher | C040 or higher |
Logger firmware:
- Deye logger — any version is compatible.
- Yingzhen logger —
LSW3_32_5406_SS_04_00.00.00.09or higher.
If anything is below the baseline, update it first. Loggers can be updated over the air once online — see Connect a logger to Wi-Fi & DeyeCloud.
2. Create the plant and bind the logger
Create (or open) the customer’s plant in DeyeCloud and add the data logger by its SN, so the inverter is online under the plant. If it isn’t connecting yet, the logger setup guide covers the common causes.
3. Register for the backstop
- Open the plant and tap Plant info.
- Tap Edit information.
- Tap Utility Connection Registration.
- Select the utility Server, then enter the device SN and the NMI.
- Generate the LFDI and Submit.
What these are:
- NMI — the National Meter Identifier for the connection point, printed on the customer’s electricity bill.
- LFDI — the device’s security identifier, generated during registration so the network can address the inverter.
Before you leave site
- Confirm the registration shows as submitted / successful in DeyeCloud.
- Have the NMI ready before you start — it’s the most common thing missing on site.
- Keep a record of the submission with the job file.
Again — verify the current firmware and process against your DNSP and Solar Victoria guidance before treating a system as compliant.